Before, our Tianjin scaffolding leasing company introduced the classification of scaffolding. One of them was called integrated scaffolding. So for the dismantling method, we are here to introduce you to the classification of scaffolding introduced by our Tianjin scaffolding leasing company. The model is called integrated scaffolding, so for the removal method, we will introduce it to you here: Yu Ou Nuo Fire Barrier Systems refers to the isolation space and related facilities which protect lives and property in order to prevent fire from burning in large area. The Rockwool Fire Barrier Clamping Plate is set in the external insulation system of combustible insulation materials. According to the horizontal direction, the non combustion insulation joint is adopted to prevent the fire from spreading along the outer wall or in the Rockwool Fire Barrier system. Rockwool Fire Barrier system,Rockwool Fire Barrier Clamping Plate,Fire Barrier Systems Zhengzhou Ou Nuo Building Materials Co., Ltd. , https://www.yuounuo.com
1. According to the framing scheme of the external wall scaffolding and considering the construction needs of other projects, the demarcation line of the scaffolding is divided, which is generally divided by the corner position or the position of the wall bar and the lateral bracing. The east façade is removed from the ○17 axis to the ○4 axis, the south façade ○A axis to the ○F axis is removed, and the west façade ○4 to 1/10 axis is removed.
2. Before partial removal of the external wall scaffold, it should be checked whether the end of the scaffold can not be removed with rigid connecting rods and lateral bracing. If there is no time, the rigid connecting wall rod and the lateral bracing must be added at the end of the scaffolding. The scaffolding can only be partially removed.
3. Afterwards, the longitudinal cross bar or the oblique shear force can be extended into the unremovable range. The steel pipe must be cut and cut at the boundary line. It is strictly forbidden to connect the short pipe after the whole root is removed.
4. When the local scaffold is removed, remove it to the end of the boundary line. At the same time, the guardrail and the safety net must be installed at the end of the unremovable end, and the scaffolding board should be laid on the flat bridge.
5. When the local scaffold is removed, when the 3 layers are removed and the height is not more than 10m, the scaffolding should not be completely inspected. Whether the scaffolding structure meets the requirements and specifications; if it does not meet the requirements, it should be adjusted accordingly to meet the specification requirements. In particular, if the fastener is loosened with the removal connection, it should be tightened.
This article is from: http://://news.chinawj.com.cn Submission: